09/28/2023 14:31 - The inspection for Site B OGD is complete and the system is online.

09/28/2023 12:42 - We will be conducting an inspection for data quality on OGB B. The system will be temporarily offline.

09/28/2023 12:41 - The routine maintenance for the UV paths is complete and all systems are online.

09/28/2023 11:22 - The UV paths will be undergoing routine maintenance fo cleaning and to replace the light sources and filters. As a result, there will be temporary downtime indicated on the system status here.

09/21/2023 21:07 - All systems are operating under normal parameters.

09/14/2023 11:02 - Argos is onsite for routine QAQC on The FTIRs and OGD.

08/10/2023 10:50 - As of 0800PST, Argos is conducting QAQC on UV 1 and 2 and TDL 3 and 4. The systems may temporarily report as offline.

08/09/2023 12:51 - We are performing routine preventative maintenance and QAQC for the PATHS 1 and 2 TDL and UV systems. The systems may reflect temporary downtime between the hours of 1300 and 1500 PST.

08/04/2023 13:23 - The FTIR will now be offline temporarily to perform routine QAQC.

08/04/2023 07:52 - The path 3 UV will be temporarily offline for work on the TDL.